Attention for all Häuslebauer: Price for evacuation/disposal overburden
Times inquire and several offers catch up - is not cheap really!
27,05 low farmer surface completely taken off, 14 containers, excavation, backfilling begun with freeze protection gravel
31.05. Base plate poured, 5 concrete mixers
03.06. Stones delivered, for boarding from base plate removes

called and informed that the wrong stones were supplied, it wants to worry 04.06. 10,00 o'clock Domus drum06.06. Wasseranschluss opened07.06. new stones supplied, carcass begins, water provisionally put on
Times inquire and several offers catch up - is not cheap really!
27,05 low farmer surface completely taken off, 14 containers, excavation, backfilling begun with freeze protection gravel
31.05. Base plate poured, 5 concrete mixers
03.06. Stones delivered, for boarding from base plate removes

called and informed that the wrong stones were supplied, it wants to worry 04.06. 10,00 o'clock Domus drum06.06. Wasseranschluss opened07.06. new stones supplied, carcass begins, water provisionally put on