Wednesday, April 4, 2007

Chronicle of a building of houses 3

01.04. Call notary - by 31.03. still nothing with the land register office received
Call insolvency manager - is to 29.03. raus
04.04. Call land register office - rewriting of one into other company is present, release from insolvency mass is missing however still
05.04. Fax at director of the district court Merseburg with request for assistance
Call insolvency manager - release at land register office goes today still raus, lies however
actually the Notarin forwards
08.04. Answer by director Amtsgericht Merseburg: after its opinion everything i.O.
09.04. Parents-in-law building of houses gebeichtet
11.04. Call of notaries, still nothing new, land register office sat down directly with insolvency court in connection and waits now for release of this
Call land register office, insolvency court and - managers already previous week written down, up to now still no reaction
Call Insolenzverwalter - copy of the release is not sufficient land register office, insolvency managers sits down tomorrow morning directly with insolvency court in connection tries clarifying
13.04. Call with the insolvency manager, has with land register office contact taken up, now is clear as and into which Forma the land register office which wishes, tomorrow sits down insolvency managers with insolvency court in connection, insolvency court must only release of properties at land register office send
15.04. Antje calls confirmation of the rewriting with insolvency manager, land register office and notary, arrived in the land register on GmbH not yet on insolvency court, afterwards release takes place via this
21,04 Antje calls with insolvency manager, letter should with the insolvency court be, recommends however there not “to nerves”
23,04 complaint of supervision of service at insolvency court Hamburg because of
“impudent” occurrence and kidnapping
25.04. Call with land register office, EVERYTHING THERE! - became except our property
“selected” forget - hectars, hectar
26.04. Complaint of supervision of service insolvency court because of “inadvertently
Schusslichkeit "
28.04. Remainder also there - goes nevertheless
19,05 building Rome requests
23,05 commencement of construction measurement there, thread stand placed building firm there, foundation engineering company with MIDEWA request continues to fill out there, only, then geht's
25.05 12,00 o'clock date with low farmer locally for arrangement overburden and surface soil: o'clock calls 13,30, beginning not today, but tomorrow zw. 9.00-10.00 o'clock
26.05 09,15 o'clock locally, low farmer appears 10,20 o'clock offer
Overburden disposal, preparation terrace